Highway work requiring road/lane/structure closures is planned; however, work may be delayed/canceled due to weather or other issues. For up-to-date information, call 511 or visit www.511Virginia.org.  

District-wide activities:

Crews will perform various activities throughout the district to include, but are not limited to bridge & guardrail maintenance, brush/tree/limb cutting, pothole/surface/shoulder work, surface treatment operations, work orders, mowing, boom axing, drainage repairs/work and roadside cleanup.

Work at specific

locations:

Appomattox County

Route 460 and 646 – Sign work.

Route 667 – Road closing. Motorists should expect delays due to a culvert replacement project. Route 667 (Hummingbird Lane) will be temporarily closed from Route 608 (Stonewall Road) to Route 668 (Little Dogwood Road). Road closure is scheduled to begin February 07, 2022 and is planned until March 11, 2022.

Please note district-wide activities above.

Campbell County

Route 29 N over NSRR, near airport – Bridge and approach work; est. comp. May 2023.

Please note district-wide activities above.

Prince Edward County

Please note district-wide activities above.

Lynchburg

Route 29/460 (Campbell Ave–Concord Turnpike) – Bridge replacement. Northbound 29/eastbound 460 speed limit 45 mph. Lane closures changes in traffic pattern are likely. Completion July 31, 2023.

Amherst County

Route 29 Bus (Lakeside Dr-Woodys Lake Rd) – Sidewalk work. Lane closures/delays. Est comp. 11/21.

Route 681 over Williams Run – Bridge rehabilitation project underway. One 10’6” lane w/signal.

Route 682 Woody’s Lake Road Madison Heights – Starting Jan 10 with an expected completion date of Dec. 15, 2022. Expect lane closures, delays, rough road. Signs and flaggers to direct traffic.

Please note district-wide activities above.

Buckingham County

Route 665 – Road closing. Motorists should expect delays due to a culvert replacement project. Route 665 (Fanny White Road) will be temporarily closed from Route 631 (Troublesome Creek Road) to Route 60 (James Anderson Hwy). Road closure is scheduled to begin Feb. 14, 2022 and is planned until March 11, 2022.

Route 743, Shady Oaks Road – Cul-de-sac work.

Please note district-wide activities above.

Charlotte County

Please note district-wide activities above.

Nelson County

Please note district-wide activities above.